(All dollar values are CDN)
Rocanville
Operations
Mining depth – 960 meters
Annual capacity – 3.0 million tonnes KCl
Products – granular and standard-grade potash
Performance
Significant Achievements
- Produced a record 2.834 million tonnes of finished product in 2008.
- Expansions led to recruiting challenges, but still hired 69 employees.
- Resolved mineral rights acquisitions for the Rocanville West project.
Environmental Initiatives
- Undertook Phase 2 of the brine pond expansion to ensure adequate brine and flood storage. Project was close to completion by year-end.
- Began upstream dike construction to increase the fine tailings pond capacity.
Community Relations
- Held on-site meetings in fall 2008 to provide information to the public about the expansion project and the Mineral Rights Unitization Agreement and process.
Community Contributions
- Cash donations to community organizations in 2008 totaled $136,274; the main recipients were Moosomin and District Health Care, Rocanville Fire Department, Town of Moosomin – Fire Hall Expansion, Welwyn Fire Department – Fire Hall Building Project, Spy Hill Lions Club, Rocanville Skating Rink, Rocanville Aquatic Centre, Rocanville Town & Country Golf Club.
- Made a corporate commitment of $500,000 to the Moosomin Health District to build a new hospital. Half this commitment was contingent on the community raising a matching $250,000.
Educational Initiatives
- Awarded three scholarships to children of employees: a corporate scholarship of $3,000 per year and two $1,000 divisional scholarships.
- Continued to participate in the University of Regina's Cooperative Education Program by hiring engineering students for work terms. Participate in a similar program with the Saskatchewan Institute of Applied Science and Technology for certain technical students.
Local Procurement
- Made local purchases in 2008 of goods, materials and services totaling $43.9 million, or 66 percent of all expenditures (excluding major expansions, raw materials, energy and transportation).
| 2004 | 2005 | 2006 | 2007 | 2008 | |
| Annual Production (000 tonnes KCl) |
1,833.7 |
2,573.3 |
1,897.1 |
2,647.0 |
2,834.0 |
| Employment | |||||
| # of employees | 328 | 340 | 343 | 354 | 406 |
| # of female employees | 21 | 22 | 24 | 26 | 30 |
| Gender ratio (% female/total employees) | 6.4 | 6.4 | 7.0 | 7.3 | 7.4 |
| Average tenure (years) | 17.1 | 17.4 | 15.2 | 14.8 | 13.5 |
| Absenteeism rate (% hours absent) | 3.5 | 2.9 | 4.5 | 5.2 | 4.6 |
| Employee training provided (hrs per employee) | 92 | 32 | 72 | 78 | 95 |
| Safety Performance | |||||
| Lost-time frequency (per 200,000 hrs) | 0.3 | 0.3 | 1.0 | 0.3 | 0.8 |
| Recordable frequency (per 200,000 hrs) | 2.0 | 2.8 | 3.0 | 6.0 | 6.0 |
| Greenhouse Gas Emissions | |||||
| GHG emissions (000 tonnes) | 61.8 | 75.9 | 58.7 | 71.6 | 77.9 |
| Normalized GHGs (GHGs/tonne production) | 0.03 | 0.03 | 0.03 | 0.03 | 0.03 |
| NPRI Air Pollutants (tonnes) | |||||
| Nitrogen oxides | 52.5 | 57.6 | 49.3 | 61.0 | 94.7 |
| Carbon monoxide | 172.4 | 222.2 | 63.5 | 83.0 | 117.7 |
| Particulates (dust) | 305.6 | 465.0 | 425.0 | 449.0 | 451.2 |
| Volatile organic compounds | 4.42 | 7.2 | 5.2 | 7.0 | 7.6 |
| Waste to Land (000 tonnes) | |||||
| Waste salt to storage | 2,543 | 3,986 | 2,799 | 3,910 | 4,156 |
| Salt in brine injection well | 694 | 665 | 643 | 786 | 690 |
| Water Use (000 m3) | |||||
| Water withdrawn | 1,001 | 1,161 | 1,058 | 1,110 | 1,036 |
| Environmental Expenditures ($ 000) |
|||||
| Operating expenditures | 7,265 | 7,359 | 6,508 | 8,997 | 8,283 |
| Capital expenditures | 389 | 489 | 3,823 | 11,145 | 22,676 |
| Energy | |||||
| Energy costs ($ million) | 19.1 | 23.9 | 17.3 | 22.6 | 26.0 |
| Energy use (TJ) | 1,830 | 2,320 | 1,835 | 2,286 | 2,446 |
| Energy efficiency (GJ/tonne production) | 1.0 | 0.9 | 1.0 | 0.8 | 0.9 |
| Procurement | |||||
| Local purchasing ($ million) | 53.8 | 40.5 | 20.3 | 26.0 | 43.9 |
| Source: PotashCorp | |||||