Potash

(All dollar values are CDN)

Patience Lake

Operations

Mining depth – solution mine at 1000 meters
Annual capacity – 1.0 million tonnes KCl
Products – white standard, lawn and garden, and granular-grade potash

Performance

Significant Events

  • Work continued on the expansion project to bring back idled capacity; many on-site service providers were accommodated, and additional resources were assigned to monitor safety.
  • Reached one year without a recordable injury in June 2008 and four years with no lost-time injuries in December.
  • Experienced a 14-week strike, and employees returned to work after a new collective agreement was approved in November.

Community Donations

  • Donated cash totaling $30,502 to local organizations in 2008. The main recipients were: Sunset Estates volunteer fire department, Saskatoon Food Bank, restoration of a 100-year old heritage building, Reflections of Nature, and SRC Master National.

Awards

  • Received the Saskatchewan Mining Association Safety Award for achieving a zero injury rating.
  • Patience Lake Emergency Response team was the overall Surface Provincial Mine Rescue Champion in 2008 for the fourth consecutive year.

Local Procurement

  • Made local purchases in 2008 of goods, materials and services totaling $14.5 million, or 68 percent of all expenditures (excluding major expansions, raw materials, energy and transportation).

  2004 2005 2006 2007 2008
Annual Production (000 tonnes KCl) 239.1 251.0 190.1 257.0 282.0
           
Employment          
# of employees 67 68 67 70 75
# of female employees 4 4 5 6 6
Gender ratio (% female/total employees) 5.9 5.8 7.5 8.6 8.0
Average tenure (years) 20.3 21.3 20.1 17.9 17.5
Absenteeism rate (% hours absent) 4.1 5.2 3.0 3.9 5.5
Employee training provided (hrs per employee) 30 40 53 112 92
           
Safety Performance          
Lost-time frequency (per 200,000 hrs) 1.76
Recordable frequency (per 200,000 hrs) 8.8 5.0 3.7 3.2 3.5
           
Greenhouse Gas Emissions          
GHG emissions (000 tonnes) 35.9 35.1 33.7 36.7 28.2
Normalized GHGs (GHGs/tonne production) 0.15 0.15 0.18 0.14 0.10
           
NPRI Air Pollutants (tonnes)          
Nitrogen oxides 36.2 36.4 35.1 38.4 30.2
Carbon monoxide 26.3 26.0 25.0 26.9 20.7
Particulates (dust) 306.0 214.1 181.3 202.6 176.2
Volatile organic compounds 2.0 1.8 1.7 1.7 1.3
           
Waste to Land (000 tonnes)          
Waste salt to storage 39.7 69.9 18.1 36.7 47.7
Waste salt and clay to mine 127.9 124.7 159.8 263.0 257.4
           
Water Use (000 m3)          
Water withdrawn 1,082 761 309 457 425
           
Environmental Expenditures ($ 000)          
Operating expenditures 1,207 535 290 542 598
Capital expenditures 451 1,503 817 3,476 3,865
           
Energy          
Energy costs ($ million) 7.2 8.5 7.6 7.6 7.2
Energy use (TJ) 860 844 803 884 720
Energy efficiency (GJ/tonne production) 3.6 3.4 4.2 3.4 2.6
           
Procurement          
Local purchasing ($ million) 2.5 3.1 3.7 5.9 14.5
Source: PotashCorp