Our Debottlenecking and Expansion Projects Should
Enable Us to Meet Expected World Demand
| Location | Investment Billion $ CDN |
Standard Capacity Added | Compaction Capacity Added | Expected Construction Completion |
| Rocanville | $0.13 | 0.75 MMT | 1.50 MMT | Complete (2005) |
| Allan | $0.21 | 0.40 MMT | 0.50 MMT | Complete (2007) |
| Lanigan | $0.41 | 1.50 MMT | 0.75 MMT | Q2 2008 |
| Patience Lake | $0.11 | 0.36 MMT | – | Q4 2008 |
| Cory | $0.89 | 1.20 MMT | 0.75 MMT | Q2 2010 |
| New Brunswick | $1.66 | 1.20 MMT | 0.75 MMT | Q4 2011 |
| Rocanville | $1.80 | 2.00 MMT | To be determined | Q4 2012 |
| Total | $5.21 | 7.41 MMT |