PREPARING FOR TOMORROW, TODAY
Anticipating the needs of tomorrow's world, we took major steps in 2007 to prepare for increased potash demand in the years to come.
In keeping with our Potash First strategy, we completed and announced projects to strengthen our potash position and add long-term value to our company. These projects will build on our current operational capacity of 10.8 million tonnes, at a substantial saving of cost and time over equivalent greenfield capacity.
Projects Underway in 2007
A 2-million-tonne, $1.8 billion mine and mill expansion at Rocanville will enhance this low-cost, technologically advanced facility.
The expansion will leverage existing facilities and infrastructure to reduce construction costs by an estimated 25 percent and completion time by up to two years over equivalent greenfield capacity. An additional shaft will be sunk, providing two shafts with ore hoisting capabilities. Mining machines, underground services and power infrastructure will be added.
A new mill will be built adjacent to the existing mill. Storage, load-out and on-site rail capability will be modified to handle increased tonnes with minimal investment. Construction is scheduled to be complete at the end of 2012.