| Facility | Capacity Expansions/ Debottlenecking 1 | Actual and Expected Investment (CDN$ billions) | Expected Remaining Spending 2 (CDN$ billions) | Actual and Expected Construction Completion 3 | Expected Operational Capability Following Ramp-Up |
|---|---|---|---|---|---|
| Construction Projects Completed (2005-2011) | |||||
| Rocanville | 0.75 MMT | $0.13 | 2005 | ||
| Allan | 0.40 MMT | $0.21 | 2007 | ||
| Lanigan | 1.50 MMT | $0.41 | 2008 | 3.6 MMT | |
| Patience Lake | 0.36 MMT | $0.11 | 2009 | 0.6 MMT | |
| Cory I | 1.20 MMT | $0.90 | 2010 | ||
| Projects in Progress | |||||
| Cory II | 1.00 MMT | $0.74 | $0.03 | 2012 | 2.7 MMT |
| Allan | 1.00 MMT | $0.77 | $0.25 | 2012 | 2.7 MMT |
| New Brunswick 4 | 1.20 MMT | $1.66 | $0.34 | 2013 | 1.8 MMT |
| Rocanville | 2.70 MMT | $2.80 | $1.35 | 2014 | 5.7 MMT |
| Total All Projects | 10.11 MMT | $7.73 | $1.97 | 17.1 MMT | |